Sample Record for 2023-06-01-63
Note: Fields with no data or with a value of "Unknown" will not be displayed on the print out.
Project Information
Project ID: 994602 DEA: 09392004 EFIS: 0922000036
QA Service Level: 1
DIST-CO-RTE-PM: 09-INY-395-44.9/50.9,52.9/54.5
Work Description: HOT MIX ASPHALT (TYPE-A), SHOULDER BACKING, AND STRIPING.
Location Description: INYO COUNTY NEAR LONE PINE FROM 1.3 MILES SOUTH OF COTTONWOOD ROAD TO 2 MILES NORTH OF BARTLETT ROAD AND FROM 0.3 MILE SOUTH OF LUBKEN CANYON ROAD TO 1.1 MILES SOUTH OF GOLF COURSE ROAD
Contractor Name: SULLY-MILLER CONTRACTING COMPANY
Contractor Address: Unknown
Resident Engineer: Unknown Structure Rep.: Unknown
Sample Information
DIME Sample ID: 2023-06-01-63
TL Number from the TL Form:
Sample Submitted By Organization: CT D09 - Bishop Field Laboratory
Sample Organization Contact: (760) 872-5211
Type of Sample: Verification
Type of Material: Aggregate
Sample Taken Date: 06/01/2023
Date that the sample was received by the laboratory/organization performing the testing: 06/01/2023
The quantity of what the sample constitutes: 2 Bags of Coldfeed & 1 Bag of RAP
A brief description of the sample: 3/4" Coldfeed Aggs
From where was the sample collected: Manufacturer
Laboratory sample identification: 3118 - JMF-01
Structure unique identifier:
Structure name:
The fabricator/manufacturer/facility name: Blue Diamond-Victorville
Material Information
Source Identification (SMARA, name of Pit or Job Site): 91-36-0022, 91-33-0046
The fabricator's/manufacturer's product name for the sample:
The fabricator/manufacturer designation for the sample:
The plant number:
A detailed description of where the material sample was collected: Sample Device at Blue Diamond Victorville Plant
Where the material sample would have been placed if not sampled:
Primary Aggregate Nominal Size: 3/4 inch
The concrete mix design number:
Lot number:
Sublot number:
Aggregate Mix Number:
Test Results
Test 1 of 5
DIME Test ID: 2023-06-01-63-1
Test Method: AASHTO T176-08: Standard Method of Test for Plastic Fines in Graded Aggregates and Soils by Use of the Sand Equivalent Test (Sand Equivalent)
Verified Date: 06/13/2023
Date Tested: 06/02/2023
Submitted By Organization: CT D09 - Bishop Field Laboratory
Organization Address: 500 South Main Street,
Organization City: Bishop
Organization State: CA
Organization Zipcode: 93514
Organization Email: chris.talbot@dot.ca.gov
Organization Phone: (760) 872-0794
General Comments for this Test: JMF-01
Test Result Compliance: complies
Additional Comments When Verified:
Test 2 of 5
DIME Test ID: 2023-06-01-63-2
Test Method: AASHTO T27-14: Standard Method of Test for Sieve Analysis of Fine and Coarse Aggregates (Sieve Analysis)
Verified Date: 06/13/2023
Date Tested: 06/02/2023
Submitted By Organization: CT D09 - Bishop Field Laboratory
Organization Address: 500 South Main Street,
Organization City: Bishop
Organization State: CA
Organization Zipcode: 93514
Organization Email: chris.talbot@dot.ca.gov
Organization Phone: (760) 872-0794
General Comments for this Test: JMF-01
RAP & Virgin Agg Combined
Test Result Compliance: complies
Additional Comments When Verified:
|
What type of gradation is being tested?
|
Combined Gradation
|
|
Cumulative percent passing the 2 in. sieve
|
100 %
|
|
Cumulative percent passing the 1 1/2 in. sieve
|
100 %
|
|
Cumulative percent passing the 1 in. sieve
|
100 %
|
|
Cumulative percent passing the 3/4 in. sieve
|
97 %
|
|
Cumulative percent passing the 1/2 in. sieve
|
86 %
|
|
Cumulative percent passing the 3/8 in. sieve
|
74 %
|
|
Cumulative percent passing the #4 sieve
|
53 %
|
|
Cumulative percent passing the #8 sieve
|
41 %
|
|
Cumulative percent passing the #16 sieve
|
30 %
|
|
Cumulative percent passing the #30 sieve
|
20 %
|
|
Cumulative percent passing the #50 sieve
|
11 %
|
|
Cumulative percent passing the #100 sieve
|
6 %
|
|
Cumulative percent passing the #200 sieve
|
3.1 %
|
Test 3 of 5
DIME Test ID: 2023-06-01-63-3
Test Method: AASHTO T304-11: Standard Method of Test for Uncompacted Void Content of Fine Aggregate (Fine of Crushed Particles)
Verified Date: 06/13/2023
Date Tested: 06/02/2023
Submitted By Organization: CT D09 - Bishop Field Laboratory
Organization Address: 500 South Main Street,
Organization City: Bishop
Organization State: CA
Organization Zipcode: 93514
Organization Email: chris.talbot@dot.ca.gov
Organization Phone: (760) 872-0794
General Comments for this Test: JMF-01
Test Result Compliance: complies
Additional Comments When Verified:
|
What test method is performed?
|
Method A
|
|
Bulk dry specific gravity
|
2.58
|
|
Average uncompacted voids
|
45.4 %
|
Test 4 of 5
DIME Test ID: 2023-06-01-63-4
Test Method: AASHTO T335-09r13: Standard Method of Test for Determining the Percentage of Fracture in Coarse Aggregate (Percent of Crushed Particles)
Verified Date: 06/13/2023
Date Tested: 06/02/2023
Submitted By Organization: CT D09 - Bishop Field Laboratory
Organization Address: 500 South Main Street,
Organization City: Bishop
Organization State: CA
Organization Zipcode: 93514
Organization Email: chris.talbot@dot.ca.gov
Organization Phone: (760) 872-0794
General Comments for this Test: JMF-01
Test Result Compliance: complies
Additional Comments When Verified:
|
Method
|
2 - Individual Fracture Determination
|
|
Aggregate Size and Fracture Type
|
Coarse 1 and 2 Faced
|
|
Weighted average percentage of fractured, coarse, 2 faced particles
|
98 %
|
|
Weighted average percentage of fractured, coarse, 1 faced particles
|
99 %
|
Test 5 of 5
DIME Test ID: 2023-06-01-63-5
Test Method: AASHTO T96-02r10: Standard Method of Test for Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine (Los Angeles Rattler)
Verified Date: 06/13/2023
Date Tested: 06/05/2023
Submitted By Organization: CT D09 - Bishop Field Laboratory
Organization Address: 500 South Main Street,
Organization City: Bishop
Organization State: CA
Organization Zipcode: 93514
Organization Email: chris.talbot@dot.ca.gov
Organization Phone: (760) 872-0794
General Comments for this Test: JMF-01
Test Result Compliance: complies
Additional Comments When Verified:
|
Grading designation
|
B
|
|
Percent loss after 100 revolutions
|
4.8 %
|
|
Percent loss after 500 revolutions
|
23.6 %
|