Print Report | Back to Sample Detail

Sample Record for 2022-03-08-35

Note: Fields with no data or with a value of "Unknown" will not be displayed on the print out.

Project Information

Project ID: 213598 DEA: 051F75U4 EFIS: 0518000092 QA Service Level: 1
DIST-CO-RTE-PM: 05-MON-101-R36.9/47.7
Work Description: CRCP, SEISMIC RETROFIT, BRIDGE WIDENING AND MEDIAN BARRIER
Location Description: MONTEREY COUNTY IN AND NEAR KING CITY FROM 0.4 MILE SOUTH OF WILD HORSE ROAD OVERCROSSING TO TEAGUE AVENUE
Contractor Name: OHL USA, INC.
Contractor Address: 1920 Main St. Suite 310, Irvine, CA 92614
Resident Engineer: Adam Rianda Structure Rep.: Unknown

Sample Information

DIME Sample ID: 2022-03-08-35
TL Number from the TL Form:
Sample Submitted By Organization: CT D05 - Big Sur Field Laboratory
Sample Organization Contact: (805) 471-2100
Type of Sample: Quality Assurance
Type of Material: Concrete
Sample Taken Date: 03/08/2022
Date that the sample was received by the laboratory/organization performing the testing: 03/08/2022
The quantity of what the sample constitutes: 70 CY
A brief description of the sample: A set of 4 CRCP beams.
From where was the sample collected: Job Site
Laboratory sample identification:
Structure unique identifier:
Structure name:
The fabricator/manufacturer/facility name: OHL KC - Mobile Batch

Material Information

The concrete mix design number: SCI-12101-4
The truck number from where the sample was collected:
The batch plant ticket number from where the sample was collected: Load 7
Concrete batch plant:
The fabricator/manufacturer designation for the sample:
A detailed description of where the material sample was collected: Batch Plant Loader Bucket
Where the material sample would have been placed if not sampled:
From Lot No.:
Bag Lot No.:

Test Results