Print Report | Back to Sample Detail

Sample Record for 2026-10-01-32

Note: Fields with no data or with a value of "Unknown" will not be displayed on the print out.

Project Information

Project ID: 1001246 DEA: 041Q7214 EFIS: 0423000277 QA Service Level: 1
DIST-CO-RTE-PM: 04-CC,CC,SOL-580,680,780-Var
Work Description: INSTALL FIBER OPTIC CABLE SYSTEM, RAMP METERING, AND WIDEN ROADWAY.
Location Description: ALAMEDA, CONTRA COSTA AND SOLANO COUNTIES AT VARIOUS LOCATIONS
Contractor Name: BAY CITIES PAVING & GRADING, INC.
Contractor Address: Unknown
Resident Engineer: Eddie Dike Structure Rep.: John parecadan

Sample Information

DIME Sample ID: 2026-10-01-32
TL Number from the TL Form:
Sample Submitted By Organization: CT D04 - Pleasanton Field Laboratory
Sample Organization Contact: (510) 224-6127
Type of Sample: Acceptance
Type of Material: Hot Mix Asphalt
Sample Taken Date: 10/01/2026
Date that the sample was received by the laboratory/organization performing the testing: 10/02/2026
The quantity of what the sample constitutes: 750 Tons
A brief description of the sample: 3/4"HMA w/25% RAP
From where was the sample collected: Source
Laboratory sample identification:
Structure unique identifier:
Structure name:
The fabricator/manufacturer/facility name: Vulcan Pleasanton Plant

Material Information

HMA Type: Type A HMA
HMA Grading: 3/4 inch
Lot number:
Sublot number:
HMA Mix Number:
Binder content (%): 4.7
Virgin binder PG: PG 58-22
Design binder PG: PG 58-22
Binder Supplier:
RAP content (%):
WMA Additives: Yes
Antistrip type:

Test Results

Test

DIME Test ID: 2026-10-01-32-1
Test Method: AASHTO T308-25: Standard Method of Test for Determining the Asphalt Binder Content of Hot Mix Asphalt (HMA) by the Ignition Method (Method A) (Asphalt Binder Content)
Verified Date: 10/05/2026
Date Tested: 10/02/2026
Submitted By Organization: CT D04 - Pleasanton Field Laboratory
Organization Address: 5675 B Gibratar Drive,
Organization City: Pleasanton
Organization State: CA
Organization Zipcode: 94588
Organization Email: dennis.yeung@dot.ca.gov
Organization Phone: (510) 224-6127
General Comments for this Test: Sample #1
Test Result Compliance: complies
Additional Comments When Verified:
What temperature unit is used? Celsius
Test procedure used? Method A
Mass of the specimen basket assembly 3562.5 g
Mass of the specimen and specimen basket assembly prior to ignition 5620.7 g
Corrected Asphalt Binder Content 4.96 %
Mass of HMA Sample prior to ignition 2058.2 g
Mass Loss 129 g
Mass of aggregate remaining after ignition 1929.2 g
Correction Factor (Percent by mass of HMA Specimen) 1.18 %
Moisture Content no data0 %
Temperature Compensation Factor 0.13 %
Test Temperature 482 C

Test

DIME Test ID: 2026-10-01-32-2
Test Method: AASHTO T30-25: Standard Method of Test for Mechanical Analysis of Extracted Aggregate (Mechanical Analysis)
Verified Date: 10/05/2026
Date Tested: 10/05/2026
Submitted By Organization: CT D04 - Pleasanton Field Laboratory
Organization Address: 5675 B Gibratar Drive,
Organization City: Pleasanton
Organization State: CA
Organization Zipcode: 94588
Organization Email: dennis.yeung@dot.ca.gov
Organization Phone: (510) 224-6127
General Comments for this Test: Sample #1
Test Result Compliance: complies
Additional Comments When Verified:
Is an aggregate correction factor used? Yes
Aggregate correction factor for the 2 in. sieve (% passing) no data0 %
Aggregate correction factor for the 1 1/2 in. sieve (% passing) no data0 %
Aggregate correction factor for the 1 in. sieve (% passing) no data0 %
Aggregate correction factor for the 3/4 in. sieve (% passing) 1 %
Aggregate correction factor for the 1/2 in. sieve (% passing) -0.2 %
Aggregate correction factor for the 3/8 in. sieve (% passing) 0.4 %
Aggregate correction factor for the #4 sieve (% passing) 0.6 %
Aggregate correction factor for the #8 sieve (% passing) 0.6 %
Aggregate correction factor for the #16 sieve (% passing) -0.5 %
Aggregate correction factor for the #30 sieve (% passing) -0.8 %
Aggregate correction factor for the #50 sieve (% passing) -0.6 %
Aggregate correction factor for the #100 sieve (% passing) -0.1 %
Aggregate correction factor for the #200 sieve (% passing) 0.4 %
Cumulative percent passing the 2 in. sieve 100 %
Cumulative percent passing the 1 1/2 in. sieve 100 %
Cumulative percent passing the 1 in. sieve 100 %
Cumulative percent passing the 3/4 in. sieve 98 %
Cumulative percent passing the 1/2 in. sieve 88 %
Cumulative percent passing the 3/8 in. sieve 80 %
Cumulative percent passing the #4 sieve 54 %
Cumulative percent passing the #8 sieve 32 %
Cumulative percent passing the #16 sieve 20 %
Cumulative percent passing the #30 sieve 15 %
Cumulative percent passing the #50 sieve 12 %
Cumulative percent passing the #100 sieve 8 %
Cumulative percent passing the #200 sieve 5.4 %