Note: Fields with no data or with a value of "Unknown" will not be displayed on the print out.
Project ID: 1002671 DEA: 09402704 EFIS: 0924000060
QA Service Level: 1
DIST-CO-RTE-PM: 09-MNO--unknown
Work Description:
Location Description:
Contractor Name: Unknown
Contractor Address: Unknown
Resident Engineer: Unknown Structure Rep.: Unknown
DIME Sample ID: 2026-09-15-68
TL Number from the TL Form:
Sample Submitted By Organization: CT D09 - Bishop Field Laboratory
Sample Organization Contact: (760) 872-5211
Type of Sample: Quality Assurance
Type of Material: Aggregate
Sample Taken Date: 09/15/2026
Date that the sample was received by the laboratory/organization performing the testing: 09/21/2026
The quantity of what the sample constitutes: Daily Production
A brief description of the sample: 3/8's Chip
From where was the sample collected: Source
Laboratory sample identification: Chip 01
Structure unique identifier:
Structure name:
The fabricator/manufacturer/facility name: Road and Highway Builders
Source Identification (SMARA, name of Pit or Job Site): Job site
The fabricator's/manufacturer's product name for the sample:
The fabricator/manufacturer designation for the sample:
The plant number:
A detailed description of where the material sample was collected: Stockpile @ Plant
Where the material sample would have been placed if not sampled:
Primary Aggregate Nominal Size: 3/8 inch
The concrete mix design number:
Lot number:
Sublot number:
Aggregate Mix Number:
DIME Test ID: 2026-09-15-68-1
Test Method: AASHTO T27-14: Standard Method of Test for Sieve Analysis of Fine and Coarse Aggregates (Sieve Analysis)
Verified Date: 09/23/2026
Date Tested: 09/23/2026
Submitted By Organization: CT D09 - Bishop Field Laboratory
Organization Address: 500 South Main Street,
Organization City: Bishop
Organization State: CA
Organization Zipcode: 93514
Organization Email: chris.talbot@dot.ca.gov
Organization Phone: (760) 872-0794
General Comments for this Test: Chips 01
Test Result Compliance: complies
Additional Comments When Verified:
|
What type of gradation is being tested?
|
HMA Gradation
|
|
Cumulative percent passing the 2 in. sieve
|
100 %
|
|
Cumulative percent passing the 1 1/2 in. sieve
|
100 %
|
|
Cumulative percent passing the 1 in. sieve
|
100 %
|
|
Cumulative percent passing the 3/4 in. sieve
|
100 %
|
|
Cumulative percent passing the 1/2 in. sieve
|
99 %
|
|
Cumulative percent passing the 3/8 in. sieve
|
71 %
|
|
Cumulative percent passing the #4 sieve
|
5 %
|
|
Cumulative percent passing the #8 sieve
|
3 %
|
|
Cumulative percent passing the #16 sieve
|
2 %
|
|
Cumulative percent passing the #30 sieve
|
2 %
|
|
Cumulative percent passing the #50 sieve
|
2 %
|
|
Cumulative percent passing the #100 sieve
|
1 %
|
|
Cumulative percent passing the #200 sieve
|
1 %
|