Projects

To search for a project, enter filter criteria in the appropriate input field below. If a project is not listed, please contact a METS Representative for assistance.
Displaying 17621-17630 of 18003 results.
Project IDProject IdentifiersDIST-CO-RTE-PMWork DescriptionLocation DescriptionCaltrans Closeout DateMETS Service LevelActions
     
210132Project ID: 210132
DEA: 080R2504
EFIS: 0812000054
Permit Numbers: 0814AOP1112
08-RIV-10-155.1/156.1Enter onto Interstate 10 (I-10) right-of-way at Hobson Way Interchange in the City of Blythe to construct new improvements including new on and off ramps approximately 3,500 feet west of the the existing ramps and to close the existing ramps, as per plan date stamped December 3, 2014 by Caltrans DiHobson Way, Blythe07/31/20182 (09/29/2015)Details CEM-3701 Report
210160Project ID: 210160
DEA: 101E2204
EFIS: 1015000011
COOP: 10439
10-SJ-580-13.3/13.8Widen existing road under I-580 to accommodate ramp widening and additional left turn lanes . Proposes to replace existing two lane bridge over the adjacent California Aqueduct on the east side of the Interchange and add two additional lanesBetween I-580 and Old Schulte Road 2 (01/30/2015)Details CEM-3701 Report
210289Project ID: 210289
DEA: 080E9504
Permit Numbers: 0814NMC0370 08156DP0455 0815NRT0491
08-RIV-15-19.45/19.71Enter onto Interstate 15 right-of-way just north of Railroad Canyon Road Interchange in the City of Lake Elsinore to remove existing PCCP and AC shoulder and to construct a new southbound JPCP deceleration lane and HMA shoulder, including minor grading, drainage inlet modification, temporary waterRailroad Canyon Road, Lake Elsinore07/31/20182 (08/04/2015)Details CEM-3701 Report
210158Project ID: 210158
DEA: 100G4204
EFIS: 1014000038
COOP: 10437
10-STA-5-15.8/15.9Reconstruct the existing Interstate 5/Sperry Road InterchangeStanislaus County 2 (01/30/2015)Details CEM-3701 Report
210152Project ID: 210152
Permit Numbers: 0813NSN0996
08---  07/31/2018NOT VERIFIEDDetails CEM-3701 Report
210155Project ID: 210155
DEA: 101E3904
EFIS: 1015000049
10-SJ-4,005-Vatr, varReplace existing irrigation systems with RICSAt various locations07/28/20212 (01/30/2015)Details CEM-3701 Report
210164Project ID: 210164
DEA: 010F0704
EFIS: 0115000063
01-HUM-101-6.5Slide removal and slope stabilizationIn Humboldt County near Benbow at 0.6 mile north of South Fork Eel River Bridge08/27/20182 (01/30/2015)Details CEM-3701 Report
210170Project ID: 210170
DEA: 010F0104
EFIS: 0115000056
01-HUM-299-24.1, 24.2Stabilize slope and reconstruct roadwayIn Hum County08/27/20182 (01/30/2015)Details CEM-3701 Report
210179Project ID: 210179
DEA: 100Y9404
10-AMA-88-38.0/46.9RUBBERIZED-HMA RESURFACING, LOCALIZED DIGOUTS, AND DIKE REPLACEMENT.AMADOR COUNTY ABOUT 8 MILES WEST OF PIONEER FROM 0.2 MILE WEST OF SHAKE RIDGE ROAD TO 0.9 MILE EAST OF CAT CREEK ROAD11/07/20162 (01/30/2015)Details CEM-3701 Report
210180Project ID: 210180
DEA: 101C9004
EFIS: 1014000185
10-STA-5,27-41.0/51.0REPAIR FAILED AREAS AND RUBBERIZED HMA RESURFACING.STANLISLAUS COUNTY AT AND NEAR LA GRANGE FROM 2.2 MILES EAST OF TOULUMNE RESORT RIGHT TO TOULUMNE COUNTY LINE.11/14/20162 (01/30/2015)Details CEM-3701 Report