Project Details

This page displays current information for project DEA: 04264724.

Project Information

Project IdentifiersProject ID: 993333
DEA: 04264724
EFIS: 0419000068
DIST-CO-RTE-PM04-MRN-101-R20.8/27.1
Award Date04/26/2022
Closeout DateNot set
Work DescriptionCIP BRIDGES, CONSTRUCT ROADWAY, RETAINING WALLS AND MODIFY ELECTRICAL.
Location DescriptionMARIN COUNTY IN AND NEAR NOVATO FROM 0.1 MILE SOUTH OF FRANKLIN AVENUE OVERHEAD TO 0.5 MILE SOUTH OF SAN ANTONIO CREEK BRIDGE
QA Service Level1 (Verified on 11/01/2021)

Caltrans Project Personnel

Personnel stored in Caltrans' project databases.

Email AddressFull NameRolePersonnel Source
Fabio.LaSerna@dot.ca.govFabio La SernaResident EngineerCaltrans RE DB
jeremy.light@dot.ca.govJeremy LightStructural RepresentativeCaltrans SR DB
waqas.ather@dot.ca.govWaqas AtherMETS REPCaltrans METS REP DB

Samples

Samples submitted for this project.

Displaying 61-70 of 622 results.
DIME Sample IDSample Taken DateSample Received DateSample TypeMaterial TypeLink
   
2022-12-22-3612/22/202212/22/2022Quality ControlAggregateView
2022-12-22-6312/22/202203/13/2023Annual Source TestingAggregateView
2022-12-22-6412/22/202203/13/2023Annual Source TestingAggregateView
2022-12-22-6512/22/202203/16/2023Annual Source TestingAggregateView
2022-12-22-6612/22/202203/16/2023Annual Source TestingAggregateView
2022-12-22-6712/22/202212/22/2022Annual Source TestingAggregateView
2022-12-22-6812/22/202212/22/2022Annual Source TestingAggregateView
2022-12-22-6912/22/202212/22/2022Annual Source TestingAggregateView
2023-01-26-3001/26/202301/27/2023Quality AssuranceConcreteView
2023-01-26-3201/26/202301/27/2023Quality AssuranceConcreteView

Job Mix Formula (JMF)

JMFs associated with this project.

JMF IDStatusSubmitted ByCreated ByDate CreatedLink
No results found.

Environmental Product Declaration (EPD)

EPDs material quantities submitted for this project.

Displaying 31-40 of 43 results.
Declaration NumberMaterial TypeVendorSubmitted byQuantity
EPD-191Carbon Steel RebarCMC - DurantC&N Reinforcing (Dawnette Galicia)22774 LBS
EPD-191Carbon Steel RebarCMC - DurantC&N Reinforcing (Dawnette Galicia)4188 LBS
EPD-191Carbon Steel RebarCMC - DurantC&N Reinforcing (Dawnette Galicia)4591 LBS
EPD-191Carbon Steel RebarCMC - DurantC&N Reinforcing (Dawnette Galicia)18649 LBS
EPD-191Carbon Steel RebarCMC - DurantC&N Reinforcing (Dawnette Galicia)12528 LBS
EPD-191Carbon Steel RebarCMC - DurantC&N Reinforcing (Dawnette Galicia)27298 LBS
EPD-191Carbon Steel RebarCMC - DurantC&N Reinforcing (Dawnette Galicia)15403 LBS
EPD-191Carbon Steel RebarCMC - SeguinC&N Reinforcing (Dawnette Galicia)82 LBS
EPD-191Carbon Steel RebarCMC - SeguinC&N Reinforcing (Dawnette Galicia)156 LBS
EPD-191Carbon Steel RebarCMC - SeguinC&N Reinforcing (Dawnette Galicia)31824 LBS

Project Summary Graphs


Samples Taken and Tests performed per Month


Number of Samples

Sample Types

Number of Tests

Test Types

Material Types

Test Methods